## What the Change Order Calculator does

A change order prices work added to or removed from a contract. It should include
labour, materials and equipment for the change, markup for overhead and profit, 
and the cost of any extra time on site, such as supervision and site costs for added
days.

## Formula

 * Direct cost = Σ hours × rate + materials
 * Change order = direct cost × (1 + markup) + extra days × daily site costs
 * Revised contract = original + approved changes + this change

## Worked example

Using the starting values in the calculator above:

  |  Input |  Value |  
   |  Original contract value |  $150,000 |  
 |  Approved changes to date |  $6,500 |  
 |  Change items |  2 entries |  
 |  Overhead and profit markup |  15% |  
 |  Extra days on site |  3 |  
 |  Daily site costs |  $400 |

  |  Result |  Value |  
   |  Change order price |  $5,030 |  
 |  Revised contract value |  $161,530 |  
 |  Direct cost of the change |  $3,330 |  
 |  Total change from original contract |  7.7% |

## How to read the result

Get every change order signed before doing the work; verbal approvals are the start
of most payment disputes.

Include time impact as well as cost, so the completion date moves with the scope.

## Related calculators

 * [Construction Overhead Calculator](https://bestwebdeveloper.org/tools/construction-overhead-calculator/):
   Calculate a construction company’s overhead rate on direct costs, the markup 
   needed to recover it and overhead per labour hour.
 * [Construction Bond Cost Estimator](https://bestwebdeveloper.org/tools/construction-bond-cost-estimator/):
   Estimate a performance and payment bond premium from contract value using a tiered
   surety rate schedule.
 * [Material Cost Estimator](https://bestwebdeveloper.org/tools/material-cost-estimator/):
   Estimate total material cost from a take-off list of quantities, unit prices 
   and waste, plus sales tax and delivery.
 * [Accessible Ramp Calculator](https://bestwebdeveloper.org/tools/accessibility-clearance-calculator/):
   Calculate wheelchair ramp length, intermediate landings and total length from
   the rise and slope, with key clearance figures.

Browse every calculator in [Contractor and Renovation Calculators](https://bestwebdeveloper.org/tool-category/contractor-calculators/),
or talk to us about [websites and lead generation for contractors](https://bestwebdeveloper.org/industries/construction-trades/).